The useful part, up front

What you’ll take away

  • A cheap charging window is useful only if its allowed power and duration can supply the required energy.
  • Feasibility is checked before cost: the original cheap-only window holds eight input kWh against a sixteen-kWh target.
  • The cheapest feasible allocation and the earliest finish can be different schedules for the same energy requirement.
  • An earlier departure or later start changes available capacity, including any partial time slot.
  • Replanning uses remaining energy and future capacity; unused hours that have passed cannot be recovered.
01

A cheap window and a departure target ask different questions

A charging timer can obey its selected hours perfectly and still leave an energy target unfinished. The timer decides when charging is permitted. The target asks how much energy must arrive before the car leaves. A cheaper unit price helps with the bill only after enough usable charging time and power are available. DOE’s managed-charging guidance treats operating schedules, electricity prices and power limits as separate inputs to that decision. [1]

We will examine one invented night, from arrival at 22:00 to departure at 06:00. The charging plan needs 16 kilowatt-hours from the electricity supply. Available power and price change during the night. First we will check whether the target is possible, then find the cheapest feasible allocation, and finally move the departure time. Every power, price and energy value is supplied for this example; no car, household tariff or scheduling product was tested.

This is a different question from whether a charger can replace a week’s driving energy. Here the challenge is placing a fixed energy requirement into particular hours. Some residential tariffs charge different rates at different times, but that is a feature of the actual tariff, not a universal rule that nighttime electricity is cheap. [3][4]

Four two-hour blocks have different power caps and prices. Original timetable: arrival 22:00, departure 06:00. Listed power is the allowed charging input cap, not a promise of energy delivery.
Original timetable: arrival 22:00, departure 06:00. Listed power is the allowed charging input cap, not a promise of energy delivery. · Ameer Journal — original explanatory diagramOriginal editorial illustration; no third-party artwork reused.
02

Put the target on the same side of the energy account as the power

Kilowatts describe a rate; kilowatt-hours describe energy delivered over time. A constant two-kilowatt input for two hours supplies four kilowatt-hours. [2] Every power and energy entry in our timetable refers to the charging input from the supply. The target is therefore 16 supply kWh. Keeping that boundary fixed lets us compare the target with available energy and multiply delivered energy by a price per supply kWh.

If we also want a battery-side interpretation, stipulate a constant conversion factor of 0.80 for this example. Then 16 input kWh corresponds to 12.8 kWh added to the modeled stored energy. Conversely, a 12.8 kWh stored-energy requirement would need 12.8 divided by 0.80, or 16 input kWh. The factor is invented and includes the entire modeled difference between input and addition; it is not a measured charging efficiency.

We will do the scheduling in the input column. That avoids charging for 12.8 kWh while actually planning to draw 16. It also avoids treating a battery percentage as an energy quantity without knowing its meaning. The required addition is taken as already established and allowed; the timetable is not choosing a recommended charge level or predicting how far the car will travel.

03

Build a capacity column for each part of the night

Divide the night into four two-hour blocks. Call 22:00–00:00 block A, 00:00–02:00 B, 02:00–04:00 C and 04:00–06:00 D. The allowed charging powers are respectively 2, 4, 3 and 1 kW. Their invented prices are $0.30, $0.20, $0.10 and $0.10 per input kWh. The lower price in the last two blocks does not imply that their available charging power is higher.

One way to construct those changing caps is to give a fictional site an aggregate six-kilowatt ceiling. Its other loads use 4, 2, 3 and 5 kW in the four blocks, leaving 2, 4, 3 and 1 kW for charging. Also stipulate a four-kilowatt charging-equipment and vehicle ceiling. This is a scheduling illustration of the building-load and power-limit considerations in managed charging, not an electrical installation calculation. [1]

Multiply each allowed rate by its two usable hours. The blocks can contribute at most 4, 8, 6 and 2 kWh. [2] These are capacities, not promises that all that energy will be delivered. A schedule may use less, stop when the target is reached, or leave an entire block unused. The capacity column is what tells us how much room each part of the night provides.

04

Check capacity before comparing prices

Across the complete connection, the four capacities add to 4+8+6+2=20 kWh. The 16 kWh target can therefore fit somewhere in the night under our rules. We have not yet decided where to place it or what it will cost. This first check answers a simpler question: is there enough possible delivery before departure, even if we use expensive hours?

Now restrict charging to the cheapest period, 02:00–06:00. Block C can provide six kWh and block D two, giving only eight. That is half the required sixteen. Multiplying the four-kilowatt equipment ceiling by all four cheap hours would give sixteen, but it would assume power that the slot constraints do not allow. The charging opportunity is limited by the usable power in each hour, not by the largest number elsewhere in the plan. [1][2]

Because the full night is feasible and the cheap-only window is not, some higher-rate energy is necessary. This does not yet tell us how much should come from each higher-rate block. It tells us that a plan advertising the lowest unit price while supplying only eight kWh cannot be compared fairly with a plan that actually supplies the target. Both cost and completion need to describe the same requirement.

The cheapest hours contain only half the required energy. Original capacity calculation: each slot lasts two hours. Maximum slot energies are 4, 8, 6 and 2 kWh; the requirement stays at 16 input kWh.
Original capacity calculation: each slot lasts two hours. Maximum slot energies are 4, 8, 6 and 2 kWh; the requirement stays at 16 input kWh. · Ameer Journal — original explanatory diagramOriginal editorial illustration; no third-party artwork reused.
05

Fill lower-price capacity before using a higher-price block

Use all eight kWh available in the two ten-cent blocks. Eight kWh still need a home. Block B can supply exactly that amount at twenty cents per kWh, so the thirty-cent block A can remain unused. The allocation is therefore A: zero, B: eight, C: six and D: two kWh. The energy charge is $1.60+$0.60+$0.20=$2.40 for the complete sixteen-kWh target.

Why is this the cheapest choice under our assumptions? Suppose a plan buys some energy at thirty cents while leaving room in the twenty-cent block. Moving one kWh into that unused room keeps the delivered total unchanged and saves ten cents. The same reasoning favors unused ten-cent capacity over twenty-cent energy. Once all useful cheaper room is filled, no such saving remains. This is our calculation using the time-dependent pricing idea described by DOE and EIA. [1][4]

In this particular case, B, C and D must all run at their allowed rates for their full durations to supply sixteen kWh without A. The last energy arrives at 06:00. Equal prices do not generally force one exact schedule, but here both cheap blocks are fully needed. The result minimizes the stated energy charge; it has not selected the earliest completion time or added a spare-time requirement.

06

Compare a prompt start with a cheaper finish

For a second policy, begin charging at the allowed maximum as soon as the fictional car arrives. Block A supplies four kWh, and B adds eight, bringing the total to twelve at 02:00. Four more kWh are needed. At C’s three-kilowatt rate, that takes one hour and twenty minutes. The target is reached at 03:20, and charging stops before D begins.

This immediate policy costs four times thirty cents, eight times twenty cents and four times ten cents: $1.20+$1.60+$0.40=$3.20. It supplies exactly the same sixteen kWh as the $2.40 allocation. The cheaper plan saves eighty cents, which is 25% of this immediate plan’s charge. These are two calculated outcomes from one invented table, not expected savings on a household bill.

The immediate policy does have another property: it finishes two hours and forty minutes before departure. The cheapest policy finishes at departure itself. Which property matters depends on the requirement being evaluated. DOE separates operating needs from cost control for this reason. [1] A price comparison should not hide the completion times, and an early-finish comparison should not imply that the energy charges were equal.

The same energy target can finish earlier or cost less. Original policies, both delivering 16 input kWh. Immediate charging finishes at 03:20 for $3.20; the minimum-cost allocation finishes at 06:00 for $2.40.
Original policies, both delivering 16 input kWh. Immediate charging finishes at 03:20 for $3.20; the minimum-cost allocation finishes at 06:00 for $2.40. · Ameer Journal — original explanatory diagramOriginal editorial illustration; no third-party artwork reused.
07

Work backward to find the last possible start

Start at the departure end of the timetable. The final two hours can provide two kWh. Add the preceding block’s six and we have eight. Add all eight from midnight to 02:00 and we reach sixteen. Therefore midnight is the latest possible start for this target and deadline, provided the allowed power is used continuously afterward. The earlier 22:00–00:00 block is unnecessary for that particular feasible plan.

Now delay the start to 00:30 with nothing charged earlier. Only one and a half hours remain in B, so it can provide six kWh instead of eight. Add C’s six and D’s two and the remaining night can supply fourteen. The target is two kWh short. A 01:00 start leaves only four kWh in B and twelve overall, making the shortfall four. A six-o’clock finish goal cannot create the lost capacity.

The cheapest plan and the latest feasible start happen to agree here because the lower-price blocks sit later and their capacities fit the target exactly. That is a feature of this table. Moving the prices while keeping the power limits unchanged could change the cheapest allocation without changing the latest feasible start. Price chooses among workable schedules; the physical delivery constraint defines which schedules are workable. [1][2]

08

An earlier departure changes both feasibility and the cheapest plan

Change the departure to 04:00 while leaving arrival, target and the earlier blocks unchanged. Block D is gone. A, B and C together can still supply eighteen kWh, so the sixteen-kWh target remains possible. The cheapest choice takes six from C, eight from B and the remaining two from A. Its cost is $0.60+$1.60+$0.60=$2.80. The earlier departure costs forty cents more in this particular comparison.

Two kWh in A takes one hour at its two-kilowatt limit. A schedule can therefore begin at 23:00, use the final hour of A, then use all of B and C to finish at 04:00. Midnight is no longer a feasible start: the two later blocks together hold only fourteen kWh. Reusing the previous start time without updating the departure would keep a familiar setting while losing the energy it was meant to provide.

Move departure earlier again, to 03:00. Now only the first hour of C is available, contributing three kWh. Even starting immediately at 22:00 gives four plus eight plus three, or fifteen kWh. No permitted allocation meets sixteen. The important boundary falls inside a block, so counting the whole two-hour block would be wrong. These changed cases show why operating-time changes require the schedule to be reconsidered. [1]

09

A finish-by control expresses a goal, not extra charging power

A start-time setting and a finish-by setting do different jobs. One selects when charging begins. The other gives a target time from which a controller may estimate a required start. As one documented example, the retrieved UK-English Model 3 manual distinguishes Start at from End by and describes calculating a start time for an end-only schedule. It also describes immediate charging in a specified insufficient-time case. [5]

That is a particular owner-manual description, not a claim that every car or wall unit uses the same rules. Our four-slot calculation is not an account of Tesla’s algorithm. The useful distinction is between the requested outcome and the inputs used to estimate when work must begin. If the car is connected late or the available power differs, an earlier estimate may no longer fit the actual opportunity.

In our original example, a midnight start works only because sixteen input kWh remain deliverable before 06:00. At 00:30, starting immediately is the best possible response for meeting that deadline, but the limit is fourteen. A controller can change a schedule within its permitted choices; a label on the screen cannot make a constrained fourteen-kWh opportunity supply sixteen. The target and the achievable result should remain separate in any interpretation of the display.

An earlier deadline can raise cost or make the target infeasible. Original separate departure cases. Arrival remains 22:00 and the requirement remains 16 input kWh; capacity after departure is unavailable.
Original separate departure cases. Arrival remains 22:00 and the requirement remains 16 input kWh; capacity after departure is unavailable. · Ameer Journal — original explanatory diagramOriginal editorial illustration; no third-party artwork reused.
10

Replan from the energy and opportunities that remain

A useful update starts with the amount still needed, not the original target in isolation. If eight input kWh have already arrived, the sixteen-kWh target has eight remaining. Compare that remainder with the power and time still available. Past energy counts toward the target; past unused hours do not remain available. DOE describes dynamic management as responding to changes in operating schedules, equipment capacity and building loads. [1]

Consider a separate change known before arrival: other loads during 04:00–06:00 will use 5.5 kW instead of five. Under the same six-kilowatt aggregate ceiling, D’s charging cap falls from one to half a kilowatt. Its two-hour capacity falls from two to one kWh. The cheapest revised allocation is A: one, B: eight, C: six and D: one, costing $0.30+$1.60+$0.60+$0.10=$2.60.

Now suppose that change becomes known only at midnight, after A has passed unused. The remaining blocks hold fifteen kWh, so the unchanged sixteen-kWh target cannot be met. Buying the extra kWh earlier would have worked if the information had been available then; it is no longer an available decision. This is why total spare capacity at arrival and spare capacity later in the night are different things.

11

Keep the conditions of the scheduling rule visible

The cheap-capacity rule worked because every delivered kWh could move independently between eligible blocks, subject to their limits. Prices were charged per input kWh, and stopping or restarting carried no extra cost. A real plan with another charging rule or a different bill structure needs those details included. For example, a charge based on the highest power during a period would introduce something beyond our simple sum of energy times price.

The same care applies to capacity. Our fictional equipment could supply any rate up to each cap, and the target fit within allowed storage. If a particular system permits only certain operating levels, or its available delivery changes with other conditions, the table must represent that behavior. AFDC describes timers and communications as features of some home equipment; their presence does not establish every control capability assumed in this mathematical example. [3]

A readable schedule therefore keeps its energy boundary, arrival, departure, available power and marginal price together. It states the selected energy in each block and checks the total before displaying a cost. Our answers then stay understandable: cheap-only charging supplies too little; the cheapest feasible plan supplies sixteen kWh for $2.40; and changing the deadline or losing a slot can change the answer. Those conclusions come from the complete timetable.

Starting after midnight loses capacity needed by 06:00. Original late-start cases with zero earlier delivery. The 16 kWh target and 06:00 departure are unchanged; each case uses the remaining allowed capacity.
Original late-start cases with zero earlier delivery. The 16 kWh target and 06:00 departure are unchanged; each case uses the remaining allowed capacity. · Ameer Journal — original explanatory diagramOriginal editorial illustration; no third-party artwork reused.
Follow the evidence

Sources & further reading

Explore the references behind this guide. External pages may change after our review.

  1. Managed EV Charging for Federal Fleets | Department of Energy
    U.S. Department of Energy · Accessed 7 Nov 2026
  2. Measuring electricity - U.S. Energy Information Administration (EIA)
    U.S. Energy Information Administration · Accessed 7 Nov 2026
  3. Alternative Fuels Data Center: Charging Electric Vehicles at Home
    U.S. Department of Energy Alternative Fuels Data Center · Accessed 7 Nov 2026
  4. Prices and factors affecting prices - U.S. Energy Information Administration (EIA)
    U.S. Energy Information Administration · Accessed 7 Nov 2026
  5. Scheduled Precondition and Charge
    Tesla · Accessed 7 Nov 2026

Article updated 7 Nov 2026.

Found something we should revisit?

Good explanations get better with thoughtful feedback.

Suggest a correction